# Interior demolition for offices and medical suites in Creve Coeur, Missouri

In Creve Coeur, Missouri, a demolition permit covers whole buildings and interior work, residential and commercial. The city form asks for an asbestos abatement report and a Waste Disposal Authorization, both from St. Louis County. Interior jobs need two sets of plans, and work must finish within 30 days of issue. The Advanced Environmental Services office is 16.2 miles away.

[Request a Quote](https://www.aes-stl.com/contact)[(314) 865-2662](tel:+1-314-865-2662)

![Aircraft hangar with a yellow fire truck and equipment during an AES PFAS project](https://www.aes-stl.com/_astro/pfas-2025-06-24-11.09.00.CKLsY786_1Qvvzs.webp)

![Worker in an orange lift working on the upper floor of a brick building](https://www.aes-stl.com/_astro/Lead-2.9LKWOFtB_1gAHyw.webp)

![AES crew member in a protective suit and orange hard hat removing wall material from scaffolding](https://www.aes-stl.com/_astro/098.hgZ7AvUK_QfCE8.webp)

## One form covers interior work

Creve Coeur's demolition permit packet covers entire structures and interior demolition, commercial and residential.

## County papers come first

The city asks for a County asbestos abatement report and a County Waste Disposal Authorization.

## Short clock

Demolition work must finish within 30 days of the permit date, so plan the sequence before you apply.

## Medical offices

The city names a strong concentration of medical offices, two hospitals and a life-science cluster.

## Creve Coeur at a glance

Office to Creve Coeur city hall

About 16.2 miles, 24 minutes without traffic

[router.project-osrm.org](https://router.project-osrm.org/route/v1/driving/-90.233935,38.599770;-90.443217,38.659897?overview=false)

City homes built before 1970

27.7%

[api.censusreporter.org](https://api.censusreporter.org/1.0/data/show/latest?table_ids=B25034&geo_ids=16000US2917272)

City homes built before 1980

50.6% (a ceiling, because the 1970s group runs past 1978)

[api.censusreporter.org](https://api.censusreporter.org/1.0/data/show/latest?table_ids=B25034&geo_ids=16000US2917272)

City housing units counted

8,821

[api.censusreporter.org](https://api.censusreporter.org/1.0/data/show/latest?table_ids=B25034&geo_ids=16000US2917272)

County asbestos report

The city demolition permit requires an asbestos abatement report or permit from St. Louis County

[crevecoeurmo.gov](https://crevecoeurmo.gov/DocumentCenter/View/512/Demolition-Permit-Requirements)

County waste authorization

The city demolition permit requires a Waste Disposal Authorization from St. Louis County

[crevecoeurmo.gov](https://crevecoeurmo.gov/DocumentCenter/View/512/Demolition-Permit-Requirements)

Interior demolition plans

2 sets of plans for commercial and residential interior demolition

[crevecoeurmo.gov](https://crevecoeurmo.gov/DocumentCenter/View/512/Demolition-Permit-Requirements)

Permit work window

Complete within 30 days after the permit is issued

[crevecoeurmo.gov](https://crevecoeurmo.gov/DocumentCenter/View/512/Demolition-Permit-Requirements)

Medical and life-science base

Mercy Hospital St. Louis, Barnes-Jewish West County Hospital and a strong concentration of medical offices

[crevecoeurmo.gov](https://www.crevecoeurmo.gov/229/Economic-Development)

Home baseAreas we serveSelect an area for its page. Map data: US Census Bureau.

## What does a Creve Coeur demolition permit ask for?

Creve Coeur’s demolition packet asks for more than a plan. It wants written utility disconnect notices, an asbestos abatement report or permit from St. Louis County, a Waste Disposal Authorization from the County, and a site plan. The form is marked “Revised 3/26/2025,” so confirm the current packet with the city’s Building Division.

The packet applies to residential and commercial work. A check box on the form covers an entire structure. Others cover interior commercial and interior residential demolition. That matters in a city where much of the work happens inside existing offices and clinics, not on empty lots.

Two County papers sit on the critical path. Order the asbestos survey early, because the County report cannot be written without it.

## Does interior demolition need a permit in Creve Coeur, Missouri?

Yes, plan on one. The city form lists interior commercial and interior residential demolition as its own types and asks for 2 sets of plans showing the scope of work. The permit also sets a clock: work must finish within 30 days after the date of issue.

A short clock rewards a tight sequence. Survey first, then abatement of anything found, then strip-out, then debris haul. If a tenant needs to stay in the next suite, AES says it tries to “contain hazardous materials to a defined construction area whenever possible” so that partial occupation can continue. Read more on our [interior demolition](https://www.aes-stl.com/interior-demolition) page and the [interior demolition](https://www.aes-stl.com/glossary/interior-demolition) glossary entry.

For commercial building demolition, the packet also requires removal of parking lot surfaces, light poles and other site improvements unless the Chief Building Official approves otherwise. Raise that in the bid, since it adds scope outside the walls.

## Why do medical and office interiors need a survey first?

Because the County will not clear the permit without one. Every structure to be demolished must be inspected for asbestos-containing material by a Missouri licensed asbestos inspector. The copy of the survey goes to the County with the demolition form, and a [NESHAP](https://www.aes-stl.com/glossary/neshap) form and commercial checklist may also be required.

Creve Coeur names a strong concentration of medical offices, Mercy Hospital St. Louis and Barnes-Jewish West County Hospital among its anchors. Many suites get remodeled over time as practices change. We have no official building-age count for these spaces, and we cannot say what any one suite contains. So the rule is simple: survey the room before you open the wall.

An [asbestos survey](https://www.aes-stl.com/glossary/asbestos-survey) samples suspect materials such as floor tile, mastic, ceiling texture and pipe wrap, then a lab reports what is in them. AES offers an [asbestos survey](https://www.aes-stl.com/asbestos-survey) and [commercial asbestos removal](https://www.aes-stl.com/commercial-asbestos-removal), and holds Missouri DNR asbestos contractor registration 27-06-0640. See also our [healthcare environmental services](https://www.aes-stl.com/healthcare-environmental-services) page.

## What do the Creve Coeur permit steps look like in order?

Work in this order, because each step feeds the next.

1.  **Survey.** A Missouri licensed asbestos inspector samples the space.
2.  **Send the County its papers.** The survey and demolition form go to St. Louis County Air Pollution Control. The County also issues the Waste Disposal Authorization.
3.  **Draw the scope.** Prepare 2 sets of plans for interior demolition.
4.  **File the city form.** Add utility disconnect notices and a site plan, then pay the city fees listed on the form.
5.  **Abate, then demolish.** Regulated material comes out first. The 30-day permit clock runs from the date of issue.

Missouri DNR also sets a state notice. It requires notice of demolitions and abatement of regulated structures at least 10 working days before crews begin. Our [Missouri demolition and renovation asbestos rules](https://www.aes-stl.com/guides/missouri-demolition-and-renovation-asbestos-rules) guide explains how that clock and the County papers fit together.

## How old are the buildings in Creve Coeur, Missouri?

Middle-aged. The 2024 American Community Survey counts 8,821 housing units in the city. About 27.7% were built before 1970 and 50.6% before 1980. The 1980 figure is a ceiling, because the 1970s group straddles 1978.

Measure

Creve Coeur

Housing units counted

8,821

Built before 1970

27.7%

Built before 1980

50.6%

Distance from AES office

About 16.2 miles, 24 minutes

So about half of the homes fall into the era when asbestos products and lead paint were common. Homes are a second thread here. Read our guides to [asbestos in older St. Louis homes](https://www.aes-stl.com/guides/asbestos-in-older-st-louis-homes) and [lead paint in pre-1978 homes](https://www.aes-stl.com/guides/lead-paint-in-pre-1978-homes) if that is your case. Remember that [friable asbestos](https://www.aes-stl.com/glossary/friable-asbestos) and bound tile need different handling.

## Does St. Louis County inspect the job itself?

Yes. County inspectors visit residential and commercial demolitions to make sure dust does not become airborne or travel beyond the property line. The County treats dust from demolition, including lead, as a public health concern. Put dust control, sealed work areas and clean exits into the plan.

For county-wide rules, see [St. Louis County, MO](https://www.aes-stl.com/service-areas/st-louis-county-mo). If the building also needs floors after strip-out, see [epoxy floor coatings](https://www.aes-stl.com/epoxy-floor-coatings) and [concrete polishing](https://www.aes-stl.com/concrete-polishing). For a full tear-down, see [demolition](https://www.aes-stl.com/demolition).

## How far is AES from Creve Coeur?

About 16.2 miles, roughly 24 minutes without traffic, from our office at 3100 Gravois Ave in St. Louis to Creve Coeur city hall. That is an OSRM free-flow estimate, so allow more at rush hour. AES takes projects within 300 miles of St. Louis and serves residential, commercial, industrial, governmental and healthcare customers.

## Next step

Call (314) 865-2662 or send the [quote form](https://www.aes-stl.com/contact) with your Creve Coeur address, the type of building and the rooms you plan to strip. Start with the [interior demolition](https://www.aes-stl.com/interior-demolition) page to see how AES scopes the work.

## Frequently asked questions

### What does Creve Coeur require for a demolition permit?

The city packet asks for utility disconnect notices, an asbestos abatement report or permit from St. Louis County, a Waste Disposal Authorization from the County, and a site plan. Interior demolition needs 2 sets of plans. The form is marked revised 3/26/2025. Call the Building Division to confirm the current packet.

### Does interior demolition need a permit in Creve Coeur?

Yes. The city demolition form has check boxes for Interior Commercial Demolition and Interior Residential Demolition, and it asks for 2 sets of plans for the scope of work. Work must finish within 30 days of the permit date. Ask the city whether your tenant buildout counts as interior demolition.

### Who checks for asbestos before demolition in Creve Coeur?

St. Louis County does. Every municipality in the county relies on the County Air Pollution Control Program to clear asbestos and other hazards before it issues a demolition permit. A Missouri licensed asbestos inspector must survey each structure, and the survey goes to the County with the demolition form.

### Are Creve Coeur buildings old enough to have asbestos?

About half of the homes may be. The 2024 American Community Survey shows 27.7% built before 1970 and 50.6% before 1980, from 8,821 housing units. We have no official age count for commercial or medical buildings, so survey each space before work begins, whatever its year.

### Does AES serve Creve Coeur, Missouri?

Yes. AES takes projects within 300 miles of St. Louis, and Creve Coeur is about 16.2 miles from our office at 3100 Gravois Ave, roughly 24 minutes without traffic. AES serves residential, commercial, industrial, governmental and healthcare customers. Call (314) 865-2662 to confirm your address and scope.

### How do I get a quote?

Call (314) 865-2662 or send the quote form at /contact with your Creve Coeur address, the building type, the floor area and the rooms you plan to strip. If you already have an asbestos survey, send it. It sets the scope and the order of work.

## Terms on this page

-   [Asbestos-containing material (ACM)](https://www.aes-stl.com/glossary/asbestos-containing-material-acm)
-   [Interior demolition](https://www.aes-stl.com/glossary/interior-demolition)
-   [Friable asbestos](https://www.aes-stl.com/glossary/friable-asbestos)
-   [Asbestos survey](https://www.aes-stl.com/glossary/asbestos-survey)
-   [Mastic](https://www.aes-stl.com/glossary/mastic)
-   [NESHAP](https://www.aes-stl.com/glossary/neshap)

## Sources

1.  [U.S. Census Bureau: ACS 2024 5-year, table B25034 (Creve Coeur city)](https://api.censusreporter.org/1.0/data/show/latest?table_ids=B25034&geo_ids=16000US2917272)
2.  [OSRM route estimate: office to Creve Coeur city hall](https://router.project-osrm.org/route/v1/driving/-90.233935,38.599770;-90.443217,38.659897?overview=false)
3.  [City of Creve Coeur: Demolition Permit Requirements (asbestos report)](https://crevecoeurmo.gov/DocumentCenter/View/512/Demolition-Permit-Requirements)
4.  [City of Creve Coeur: Demolition Permit Requirements (waste authorization)](https://crevecoeurmo.gov/DocumentCenter/View/512/Demolition-Permit-Requirements)
5.  [City of Creve Coeur: Demolition Permit Requirements (interior plans)](https://crevecoeurmo.gov/DocumentCenter/View/512/Demolition-Permit-Requirements)
6.  [City of Creve Coeur: Demolition Permit Requirements (30 days)](https://crevecoeurmo.gov/DocumentCenter/View/512/Demolition-Permit-Requirements)
7.  [City of Creve Coeur: Demolition Permit Requirements (commercial site items)](https://crevecoeurmo.gov/DocumentCenter/View/512/Demolition-Permit-Requirements)
8.  [City of Creve Coeur: Demolition Permit Requirements (approval)](https://crevecoeurmo.gov/DocumentCenter/View/512/Demolition-Permit-Requirements)
9.  [City of Creve Coeur: Demolition Permit Requirements (form date)](https://crevecoeurmo.gov/DocumentCenter/View/512/Demolition-Permit-Requirements)
10.  [City of Creve Coeur: Economic Development](https://www.crevecoeurmo.gov/229/Economic-Development)
11.  [St. Louis County Public Health: Demolition Inspections (clearance)](https://stlouiscountymo.gov/st-louis-county-departments/public-health/environmental-services/air-pollution-control/demolition-inspections/)
12.  [St. Louis County Public Health: Demolition Inspections (survey)](https://stlouiscountymo.gov/st-louis-county-departments/public-health/environmental-services/air-pollution-control/asbestos/asbestos-neshap-notification-form-instructions/)
13.  [St. Louis County Public Health: Demolition Inspections (NESHAP form)](https://stlouiscountymo.gov/st-louis-county-departments/public-health/environmental-services/air-pollution-control/demolition-inspections/)
14.  [Missouri DNR: Asbestos contractor registrations](https://dnrservices.mo.gov/env/apcp/asbestos/contractors/index.php)

Checked against the sources above on November 6, 2026. Rules and fees change, so check the linked page before you act.